| # | Summary | Link | Date |
1. | As a one-time solution for the project ‘23776 St Paul's school. FLEISCHNER FAMILY ADMISSIONS CENTER,' a non-standard Shadow Box position was approved, and due to a change in the mounting place, the lengths of pre-cut Shadow Boxes differed from the default rules. | 3/28/2024 | |
2. | As an update to the one-time solution for the project '18166 Phase 2 – Jackson Place', in addition to Sulfur Yellow RAL1016 (AAMA 2605) for Shadow Box MC063, the Azure Blue RAL5009 (AAMA 2605) color has been approved for Shadow Box MC063 and SB40, including cap profiles, end plates, and screws. | 10/16/2025 | |
3. | As a one-time solution for the project ‘16866 The Highbridge - 1387 University Ave, Bronx, NY,’ it was approved to position the shadow box 18 mm from the head to avoid interference with the lintel flashing (ID-0000028-148.V2). | 3/24/2025 |