SOP How to release a mock-up
How to release a mock-up VISION: This process was created to allow Estimators with no experience of how to release a Mock-up to familiarize themselves with the process and to release a Mock-up into production. COMMITMENT: This applies to all ...
Louvers
# Summary Link Date 1. A one-time solution has been approved for the project '15821 at 784 Courtlandt Ave.' to use 90-degree glazing beads for narrow louvers in two window positions, while standard glazing beads will be used for the IGU below. OTS #1 ...
Trickle Vents
# Summary Link Date 1. For the one-time solution on project '1405 Boston Rd - HOMEE Project,' drawing ID-0000028-119 details the placement of two trickle vents on the sash bottom. The minimum sash width is 687 mm, with vents placed 77 mm from the ...
Wash anchor
# Summary Link Date 1. As one-time solution for the project ‘24992 Livonia Site C3-The Bridge' the Wash anchor can be installed into the 6002 window frame next to the 6003 sash. OTS #3 10/29/2024
Size limitations
# Summary Link Date 1. As a one-time solution for the project '23500 27th and Tschache Lane' window positions with narrow Integral Mullions were allowed. OTS #4 11/5/2024 2. As a one-time solution for the project '20087 The Pinnacle North Bethesda' ...