| # | Summary | Link | Date |
1. | As a one-time solution for the project ‘23636 280 8th Avenue', drawings for Corner mullion 2304 + frame 8001 has been updated, including a version without widening, new screw hole placements, and added dimensions. | OTS #28 | 7/8/2024 |
2. | As a one-time solution for the project ‘18224 Cooper Park Commons B2 - Maspeth Ave’, the standard 90° corner mullion was adapted for use at 94° and 86° angles. Custom production and installation drawings (ID-0000028-156-1 and ID-0000028-156-2) have been created. | 6/4/2025 | |
3. | As a one-time solution for the project P26434 Hub Madison - Johnson & Broom, the drawing ID-0000028-188.V1 has been created for corner undersill gap issues. The solution addresses the incorrect corner mullion extension. | 1/13/2026 | |
4. | As a one-time solution for the project P27938 Coney Landing – 2955 W 28th St, project-specific installation and production rules were prepared for the angle mullion at the knee wall. Drawing ID-0000028-212 defines the required production modifications and provides instructions for the correct on-site installation and sealing for position SF-2e, 2d, 2c.2 S7/S6. One undersill is to be supplied with the project, and the required bracket and screws must be included. CANCELLED | 7/9/2026 | |
5. | As a one-time solution for the project P27938 Coney Landing – 2955 W 28th St, solution was prepared for the extended EZ mullion and widening at the knee wall. Drawing ID-0000028-213 defines the required length rules and production modifications for position SF-2e, 2d, 2c.2 S7/S6. Installation and sealing remain standard. | 7/17/2026 |